Section three - schedule of works
3.1 - Agents must produce a detailed specification/schedule of works based on the information issued by the grant officer. The specification shall be produced in full consultation with the client, grant officer and occupational therapist. The scheme of works will require written agreement from all parties prior to the required tender procedure.
3.2 - The schedule of works must include details of any specialist equipment, in consultation with the occupational therapist, who may provide quotes from suppliers.
3.3 - The schedule of works must state quantities of materials, such as, stating areas of tiling, decoration.
3.4 - Alterations to schedule of works after occupational therapist and grant officer approval may result in additional work for the agent but should be covered by the likely increase in the approval amount and therefore agent’s percentage.